Current job profile:

linde india limited (formerly boc india limited) :
Name of the project :
Construction of new 2000tpd oxygen plant at jajpur, orissa

Period from january 2013 till date

Job description:

As a sr. Project planning engineer, job responsibility involves planning work for total project, qaqc, execution of total civil work, coordination with client and contractors.

Name of the project :

Construction of new 64tpd oxygen plant at colombo.

Period april 2011 to december 2012

Job description:

As a construction manager (external designation for jobs executed within group companies), job responsibility involves execution of total civil work, site administartion, coordination with client and contractors. Receipt of materials from colombo dock. Coordination with ceylon oxygen officials for various site related matters. Site administration to control a team size of 40 persons including engineers, specialized welders.

Previous job profile:

premco rail engineers limited:
From november 2008 to march 2011

Name of the project :

Development/ construction of railway yard facilities under expansion plan of sail-isp

Location : iisco steel plant, burnpur (dist. burdwan, west bengal)

Responsibility :

Working as a project manager executing job valued 115cr. In modernisation of iisco steel plant under sail at burnpur, west bengal. The work includes construction of service buildings, diesel loco shed, tower wagon shed, road over bridge, rcc drain & underground rcc tunnel, foot over bridge, road, track work, ohe work. Responsible for progress and completion of work in line with cost, time, quality and safety. Day to day dealings with clients, contrctors, maximum utilisation of available resources, proper allocation of manpower to get maximum productivity, stores management, coordination with head office, cost control, interaction with local bodies are the various aspetcts of job.

larsen & toubro limited, ecc division:

construction of 220/ 132kv gas insulated substation under bhilai steel plant, sail.

Period : september 2007 to october 2008

Responsibility :

Initially worked as a site engineer (civil) involves in construction activities. Later worked as qaqc incharge of site, monitoring and maintaining quality of work for both civil and electrical at site. Job includes preparation of inspection test plan, method statement and product quality checking procedure for civil and electrical works and time to time training about quality norms, importance of quality in works. Responsibility also includes regular site inspection, internal audits and preparing compliance reports, calculation of design mix and approval of the same from client. Testing of bricks, soil (compaction), cement, aggregate (sand and stone chips), concrete cube at site laboratory. Physical inspection of all sorts of incoming materials at site immediately after receipt and maintaining proper record for internal and client billing purpose.

construction of 220/ 66/ 11kv substation under bhutan power corporation limited

Period : may 2007 to august 2007

Responsibility :

Working as a site engineer (civil) involving in construction of substations. Continuous chasing to contractors for timely completion of job with proper safety and quality. Also involves in planning of civil jobs, co-ordination with sub-contractor client (bpcl) and consultant (pgcil) for smooth operation of job.

APDRP under ASEB

Period: july 2005 to april 2007

Responsibility :

Working as a site engineer (civil) involving in construction of 33kv substations. Job involves planning and billing (including extra items) and execution including quality management of site for civil jobs,. Negotiating rates with sub-contractor for civil work of items and approval of the same from sector spm ( regional office), analysis and approval of client rates, obtaining completion certificate from client for smooth closing of job.

33/ 11kv distribution system under wESCO, sambalpur, orissa.

Period: from august 1999 to june 2005

Responsibility :

As a site engineer from august 1999 to december 2000 involves in construction of 33/ 11kv substations. Obtained completion certificate after handing over of substations to client. Worked as a asst. Planning & billing engineer from december 2000 to june2005 involves in 1) quantification of materials, raising of material requisition and follow up for the same for realisation,2) sub-contractor billing, client billing 4) preparation of progress reports,6) job cost report, rate analysis and all types of complience reports required at regional office as well as head quarters; maintaining actual cost estimate as well as cost control in the project; material management for the project.

Educational qualification:

Diploma in civil engineering :

Board - west bengal state council of technical education

Year of passing 1999